New Apartment Inspection in Israel Before Handover: What to Check, What You Can Demand, and the Legal Timelines
New apartment handover in Israel: home inspection, handover protocol, defect and warranty periods, notice deadlines and the contractor's duty to repair.
This story was written with AI assistance, based on the sources linked at the end, and fact-checked. Responsible editor: אריאל סיבקוב. Found an error? Tell us.
Translated from the Hebrew original with the assistance of AI. Read the Hebrew original
In short: On handover day, every defect recorded in the protocol is stronger than a defect you discover six months later. Bring an engineer or certified inspector, photograph everything, and make sure every defect is written down. After handover, two periods set by Israeli law begin: a defect period ("bedek," one to seven years depending on the type of defect), during which the contractor must repair, and a further three-year warranty period. Every notice to the contractor – in writing, with a date and photos.
Contents
- What a home inspection is and why to do it before handover
- What the law says: defect period and warranty period
- Table of defect periods by type of defect
- When and how to notify the contractor
- The contractor's right to repair – and what if it doesn't
- Handover-day checklist
- What you can demand on handover day
- Common mistakes
- Glossary
- Frequently asked questions
What a home inspection is and why to do it before handover
A home inspection ("bedek bayit") is an engineering examination of the apartment by an engineer, technician or certified inspector, ending with a detailed defects report with photos and a repair-cost estimate. It can be done at two points: before or at handover, so the defects are recorded in the handover protocol; and toward the end of the first defect year, to catch defects that appeared with use (dampness after winter, cracks, drainage).
Why does it matter? Under the law, defects that could have been found by a reasonable inspection at handover must be reported to the contractor within one year of handover. An early professional report turns "I think there's a problem" into a documented list that is hard to argue with.
What the law says: defect period and warranty period
Israel's Sale (Apartments) Law defines two periods:
The defect period – begins on the day the apartment was made available to you, and its length is set in the schedule to the law by type of defect: between one and seven years. During this period the seller must repair any non-conformity found, unless it proves the buyer caused it. The burden of proof, for the most part, is on the contractor.
The warranty period – three further years starting at the end of the defect period for that defect. During this period the contractor is still liable, but you must prove the defect stems from design, workmanship or materials. In practice this requires an expert opinion.
Material non-conformity – a defect in the load-bearing and load-transferring parts of the building that affects stability and safety. For such defects the law gives much longer protection; according to HON, up to about twenty years under the law's conditions.
Table of defect periods by type of defect
According to HON's summary from October 2026, in the commonly accepted version of the schedule:
| Type of defect | Defect period |
|---|---|
| Any other non-conformity that is not material | 1 year |
| Carpentry, metalwork and interior flooring | 2 years |
| Boilers and machinery, yard development, thermal insulation | 3 years |
| Plumbing and waterproofing (dampness) | 4 years |
| Wide cracks in non-load-bearing elements | 5 years |
| Peeling of exterior cladding | 7 years |
Note: the schedule has been updated over the years. In the version published in the official gazette in the early 1990s, for example, dampness in the roof and walls appeared at 3 years and through-cracks in walls at 5 years. The differences are small, but before legal proceedings, check the current wording with a lawyer.
When and how to notify the contractor
The law distinguishes between two kinds of defects:
- A defect that a reasonable inspection could find on handover day – must be reported within one year of handover.
- A hidden defect – must be reported within a reasonable time after you discovered it.
How to notify: by letter or email to the contractor's official address, with a description, location, date of discovery and photos. Keep a copy and proof of delivery. A phone call is not notice. Defects in common property (roof, cladding, stairwell) are usually handled jointly through the building committee.
The contractor's right to repair – and what if it doesn't
Under the law, when a repairable non-conformity is found, the contractor must be given a reasonable opportunity to repair it, and must carry out the repair within a reasonable time. In practice: don't repair it yourself before giving the contractor the opportunity, or you may lose the right to claim reimbursement.
If the contractor ignores you:
- Send a warning letter with a reasonable deadline for repair.
- Document every visit, every partial repair and every defect that returned.
- You can file a complaint with the Registrar of Contractors.
- You can sue – for small amounts in small claims court, and for large amounts with a lawyer and an expert opinion.
Before renovating (breaking a wall, replacing flooring) – coordinate with the contractor and document, so you don't destroy the evidence.
Handover-day checklist
Documents: Form 4 or a completion certificate, the sale specification attached to the contract, plans, maintenance instructions and manufacturer warranties for systems.
Structure and finishes: cracks in walls and ceilings, wall flatness, flooring (settling, hollow tiles, grout), cladding, paint.
Waterproofing and dampness: signs of dampness around windows, in showers, on balconies and in the safe room; drainage slopes on balconies and in showers.
Plumbing: water pressure, drainage of every sink and toilet, solar or electric water heater, leaks under sinks.
Electrical: all sockets and switches, a labeled electrical panel, a working residual-current device.
Openings: windows and shutters open and close, sealing, the entrance door, the safe-room door and blast window.
Systems: air conditioning (preparation or unit), intercom, gas.
Conformity to the specification: apartment size, height, number of sockets, type of flooring and kitchen – exactly as in the contract.
What you can demand on handover day
- Record every defect in the protocol, including the inspector's report as an appendix. Don't sign a "clean" protocol when there are defects.
- Receive the apartment conforming to the specification. Non-conformity to the specification is a non-conformity under the law.
- Refuse a blanket waiver. According to HON, the provisions of the law can only be varied in the buyer's favor, so a clause in which you waive defect rights in advance may be problematic. Don't sign a waiver without advice.
- Get a written timetable for repairing the recorded defects.
Common mistakes
- Handover without a professional inspector, "because the apartment looks fine."
- Reporting verbally only.
- Repairing yourself before the contractor had an opportunity.
- Skipping an inspection toward the end of the first year, after winter.
- A scattered document file: keep one digital file with the protocol, the specification, the notices, repair confirmations and dated photos.
Glossary
- Home inspection (bedek bayit): an engineering examination of the apartment by an engineer or certified inspector, ending in a documented defects report.
- Handover protocol: the document signed on key handover day listing the defects found. Every defect recorded in it is documented.
- Non-conformity: any gap between the apartment you received and what was promised in the contract, the specification or the legal requirements.
- Material non-conformity: a defect in the frame and load-bearing parts that affects the building's stability and safety.
- Defect period: the period from handover during which the contractor must repair, with the burden of proof mostly on it.
- Warranty period: the three years after the defect period, during which you must prove the defect stems from the construction.
- Sale specification: the contract appendix describing the apartment's materials, dimensions and systems. The basis for any non-conformity claim.
- Form 4 / completion certificate: the official approval that the building is fit for occupancy and connection to electricity and water.
- Common property: the parts of the building that don't belong to a particular apartment, such as the roof, stairwell and exterior cladding.
Frequently asked questions
How much does a home inspection cost? There is no official price. It depends on the apartment's size, the area and the scope of the inspection. Compare several quotes, and ask for a sample report before ordering.
Can I refuse to accept the keys because of defects? That is a legal question that depends on the severity of the defects and the contract. In most cases the safe route is to accept the apartment, record everything in the protocol and demand repair. Before refusing – consult a lawyer.
Dampness appeared after two years. Can I still demand repair? According to HON's table, the defect period for plumbing and waterproofing is 4 years. Notify immediately, in writing.
The contractor repaired it and the defect came back. Now what? Document the recurrence and notify again in writing. A defect that returns after repair strengthens the claim that the contractor did not repair properly, and justifies advice about repairing at its expense.
What about defects in common property? They concern the whole building. The building committee coordinates notices and follow-up, preferably with a joint engineering report.
Is a home inspection worthwhile for a second-hand apartment too? Yes, but the framework is different: the Sale (Apartments) Law and its defect periods apply to a new apartment from a contractor. For a second-hand apartment, the inspection mainly helps in price negotiation and renovation planning, before signing.
Who should be present on handover day? You, your inspector and the contractor's representative. Ask the representative to sign the protocol and the defects list, and keep a signed copy.
How long does handover take? For an ordinary apartment, plan for several hours, so the inspector can go through every room and every system without pressure.
This guide is general information and not legal or engineering advice.
Disclosure: ESH27, the publisher of 27news, operates in renovation and construction.
27news Editorial · Editor: Ariel
Translated from the Hebrew original with the assistance of AI.
Sources
Report an error
This story was written with AI assistance and fact-checked. Editor: Ariel. Publishing & oversight policy