Israel's construction input index rose 3.9% in a year, but builders talk of 20%: what it means for off-plan buyers

Construction wages rose 5.3% a year, oil jumped 45% and contractors report costs 20% above pre-war levels. What it means for buyers, builders and tenders

Published: · 4 min read

This story was written with AI assistance, based on the sources linked at the end, and fact-checked. Responsible editor: אריאל סיבקוב. Found an error? Tell us.

Translated from the Hebrew original with the assistance of AI. Read the Hebrew original

Israel's Central Bureau of Statistics (CBS) residential construction input index rose 0.4% in October 2026 to 104.4 points, up 3.9% over 12 months. On paper, that is a moderate rise. On the ground, contractors and appraisers describe a much wider gap: on some projects, execution costs are now 20% or more above their level on the eve of the war. Off-plan buyers feel it through indexation; builders feel it in their margins.

What the official index shows

According to the CBS, the index stood at 104.0 points in September (base: July 2025 = 100), up 2.8% since the start of the year, and added another 0.4% in October. By a calculation published in Globes on November 22, the index rose about 11.8% from September 2023 to October 2026.

The main driver is wages. The CBS release on the September index (October 15) said the 3.6% annual rise stemmed mainly from a 5.3% increase in wage prices. According to Globes, labor makes up about 41.8% of the index basket and materials and products about 44.2%, together almost 86%.

Materials show a mixed picture. In September, construction rebar rose 3.1% and mesh and cages 3.0%, while plaster and skim coat fell 2.9% and ready-mix concrete 0.9%. In October, according to Globes, rebar rose again by 1.2% and blocks by 2.1%, but the materials index as a whole rose only 0.1%.

Why it looks different on site

Dekel Group, which publishes construction price lists, calculated for Globes the direct cost per square meter (before VAT) of an eight-storey residential building in Ra'anana. In September 2023 the cost was NIS 5,528, in September 2025 NIS 6,337, and in November 2026 NIS 6,870. That is an extra NIS 1,342 per square meter, about 24.3% in three years: roughly 14.6% in the first two years of the war and another 8.4% since.

Dekel CEO Itai Schneider says the war hurt raw-material availability and logistics. "With the outbreak of the war, supply chains were disrupted," he told Globes. He also sees signs of slowing: fewer construction starts and more competition among contractors, manufacturers and importers.

Amit Gottlieb, chairman of the Builders Association's Tel Aviv and Central district, estimates that for some contractors costs have risen 20% to 25% since the war began. He says the shift to foreign workers adds housing, medical insurance and fee costs, not just wages.

Energy, financing and time

Oil is another factor. According to Globes, a barrel traded at about $64 in November 2025 and about $93 in November 2026, a rise of about 45%. The effect is neither immediate nor uniform, but it arrives through diesel for transport, energy-intensive production such as cement, glass, ceramics and metals, and petrochemical inputs such as plastic pipes and sealants.

Financing has also become more expensive. Interest rates remain high relative to pre-war levels, projects take longer, and sales promotions with deferred payments increase developers' credit needs. According to Bank of Israel data cited in the article, credit from the five largest banking groups for residential project finance rose from about NIS 49 billion at the end of 2024 to about NIS 69 billion at the end of 2025, roughly 40%.

Appraiser Shmulik Cohen estimates that about three quarters of the extra cost comes from materials and labor, and the rest from financing, consultants and lengthy planning procedures.

The gap between cities

The Land Appraisers Association estimated in June 2026 the direct construction cost at about NIS 11,100 per square meter for a tower in central Tel Aviv and about NIS 12,700 for a multi-storey building there, compared with about NIS 7,500 in Ramat Gan and Givatayim and about NIS 5,800 in Haifa. According to the association's chair, Nechama Bogin, Tel Aviv leads because of long timelines, logistical constraints and shorter working hours.

What it means for you

Off-plan buyers: In many contracts, part of the unpaid balance is linked to the construction input index, so every rise in the index rolls directly into the next payments. Check in your contract which part of the price is linked, from when and at what rate, and consider paying early if it makes sense. The November index is expected in mid-December.

Contractors and developers: Profit is highly sensitive to cost increases. In Cohen's example, a project costing NIS 100 million with revenue of NIS 113.42 million earns NIS 13.42 million. If costs rise 10% and revenue stays fixed, profit falls to NIS 3.42 million. If only NIS 60 million of the budget is execution cost that rose, profit stays at NIS 7.42 million. A senior executive at a construction company told Globes it had to ask to reopen contracts on almost all its projects.

Tender bidders: Anyone bidding today in a land or construction tender must price not only today's costs but two to three years of exposure to wages, energy and financing. The official index captures only part of that risk. In long construction contracts, check in advance whether there is an indexation or price-adjustment mechanism, and which index it relies on.

The bottom line: the official index shows a steady but moderate rise, driven mainly by wages. Field estimates are much higher, but they rest on a single model and industry testimony, not an official survey.

Report an error

Spotted a factual error, a wrong quote or a broken link? Tell us. Every report is reviewed.

You are not legally required to provide these details. Fields marked * are needed to handle your request; without them we cannot reply. Purpose: to check the error report and update you. Database controller: אריאל סיבקוב (27news), news@esh27.com. Details are not shared with others, except infrastructure providers that store them for us (Cloudflare). You may access and ask to correct your data (sections 13–14 of Israel’s Privacy Protection Law). More: privacy policy.

This story was written with AI assistance and fact-checked. Editor: Ariel. Publishing & oversight policy

More in Construction, Real Estate & SettlementWhole desk →

Offices to homes by the metro: Israel's conversion committee deposits plan for 400 apartments in Givat Shmuel

The Metropark plan would turn an office site at the Coca-Cola junction into two 32-storey towers with 400 apartments, half of them small. The city objects.

23 November 2026

Sde Dov: Luzon Ronson sold more apartments than ever in Q3, but smaller and cheaper per square meter

Luzon Ronson signed 16 contracts at its Sde Dov project in Q3 at about NIS 64,000 per sqm. What is behind the drop, and where the soil contamination stands

23 November 2026

Record collapses in Israeli construction: about 815 building and infrastructure firms failed in 2026, and listed builders' profitability was cut by more than half

CofaceBDi survey: about 815 Israeli construction and infrastructure firms collapsed in 2026, 85% more than in 2022. 93% of contractors report higher costs.

23 November 2026

Israel's 8% purchase tax on investment apartments stays until February 10, 2027: what is known and what may change

The temporary order due to expire in December was extended automatically. What a second apartment costs, what may follow in February, and why timing a deal on guesses is risky.

22 November 2026