From factory land to data center: Enlight and Shemen sign a NIS 500 million-plus lease in Haifa – but the grid connection is not yet secured

Enlight and Shemen Real Estate plan a data center of up to 150 MW in Haifa, at NIS 433,000 rent per dunam a year. It all hinges on the Electricity Authority

Published: · 5 min read

This story was written with AI assistance, based on the sources linked at the end, and fact-checked. Responsible editor: אריאל סיבקוב. Found an error? Tell us.

Translated from the Hebrew original with the assistance of AI. Read the Hebrew original

Enlight Renewable Energy and Shemen Yielding Real Estate signed an agreement on 16 November 2026 to jointly develop a data center with planned capacity of up to 150 MW in the Hof Shemen area of Haifa, in the hinterland of Haifa Port. According to the companies, cumulative rent over roughly 25 years is expected to exceed half a billion shekels. But before any concrete is poured, the Electricity Authority must issue a final decision on connecting data centers to the grid, and that decision is still a proposal under public hearing.

The deal illustrates a growing market trend: owners of industrial and logistics land are discovering that their most valuable asset is no longer the plot itself, but the ability to connect it to the power grid.

What was signed

  • The site: about 82 dunams owned by Shemen Yielding Real Estate (formerly Shemen Industries). The area actually allocated will be 41 to 57 dunams, or the full 82, depending on the grid capacity approved and on planning considerations.
  • The structure: a joint project company, initially 50% each. Enlight leads development, construction and operations, and development costs are shared equally. According to Bizportal and Globes, the initial development budget is about NIS 100 million.
  • The rent: a lease of about 25 years at annual rent of about NIS 433,000 per dunam, linked to the consumer price index from signing.
  • Option: Enlight, or an affiliate, has an option to acquire half of the rights in the allocated land at no less than NIS 6.3 million per dunam.
  • Guarantees: bank guarantees currently estimated at about NIS 334 million in total, provided in equal shares.

Shemen Yielding Real Estate, traded in Tel Aviv, held 12 properties and projects at the end of the second quarter of 2026, according to the announcement. Enlight, traded in Tel Aviv and on Nasdaq, has operated since 2008. Enlight CEO Adi Leviatan described data centers as a significant growth engine that builds on the company's energy platform. Shemen CEO Dan Sheffi said the partnership allows the site's full potential to be realized.

What it is worth to the landowner

The math depends on the size of the allocated area. On all 82 dunams, rent reaches about NIS 35.5 million a year. On 41 dunams it is about NIS 17.8 million a year. Over 25 years, before CPI linkage, the range is roughly NIS 444 million to NIS 888 million. The "more than half a billion" estimate therefore depends on the final area and on indexation.

Beyond the rent, Shemen could also receive proceeds from selling half of the land rights if the option is exercised. According to Bizportal, the company expects not to consolidate the project company in its financial statements.

The bottleneck: power, not land

According to the companies' announcement, an application for a 150 MW connection has been filed. So far only confirmation that the application documents are complete has been received, which is not a connection approval. The project's progress depends on a binding Electricity Authority decision and further approvals.

The wider context: according to Bizportal, the Electricity Authority has received data center connection requests totaling about 27,000 MW, far beyond what the power system can supply. Handling of large requests has been frozen, and the Authority's proposed decision includes:

  • A new quota of up to 1,000 MW for data centers, on top of about 2,000 MW already approved, plus up to 300 MW separately for local needs.
  • A cap of 200 MW per facility, consumption equivalent, according to Bizportal, to about 40,000 households.
  • A guarantee of NIS 2 million per requested megawatt, returned gradually according to milestones.
  • In extreme events, supply to data centers could be curtailed for up to 200 hours a year, but not below 30% of the connection size.

Israel is not alone. According to figures cited by Bizportal, data centers consume about 22% of Ireland's electricity, and Amsterdam froze connection requests for a year before setting a cap.

The Environmental Protection Ministry objects

The proposal is not going through quietly. In a letter to the Electricity Authority and the Energy Ministry, reported on 16 November, the Ministry of Environmental Protection estimated that the quota would raise air pollutant emissions by more than 10%, cost the economy about NIS 3 billion a year and bring forward the depletion of gas reserves by two to three years. The ministry wants data centers to be required to use clean energy. According to Globes, the Haifa project currently includes no new power generation, and Enlight is examining generation and storage within the compound, subject to feasibility.

What it means for you

For industrial landowners: the deal provides a public reference point for leasing land to data centers. But the value exists only with a grid connection, and connections are currently rationed.

For investors in both companies: this is a conditional deal. Most of the rental income depends on a final Authority decision, followed by permits and financing. According to Bizportal, the intention is project finance based on the project's own cash flow.

For electricity consumers: every megawatt allocated to data centers is part of the competition for the economy's generating capacity. The dispute between the Electricity Authority and the Environmental Protection Ministry will determine how much of the quota materializes, and on what terms.

What comes next

The next step is the Electricity Authority's final decision on the quota and allocation rules. Only then will it become clear whether Hof Shemen gets its 150 MW, and how much of the 82 dunams actually becomes a data center.

Report an error

Spotted a factual error, a wrong quote or a broken link? Tell us. Every report is reviewed.

You are not legally required to provide these details. Fields marked * are needed to handle your request; without them we cannot reply. Purpose: to check the error report and update you. Database controller: אריאל סיבקוב (27news), news@esh27.com. Details are not shared with others, except infrastructure providers that store them for us (Cloudflare). You may access and ask to correct your data (sections 13–14 of Israel’s Privacy Protection Law). More: privacy policy.

This story was written with AI assistance and fact-checked. Editor: Ariel. Publishing & oversight policy

More in Construction, Real Estate & SettlementWhole desk →

Offices to homes by the metro: Israel's conversion committee deposits plan for 400 apartments in Givat Shmuel

The Metropark plan would turn an office site at the Coca-Cola junction into two 32-storey towers with 400 apartments, half of them small. The city objects.

23 November 2026

Sde Dov: Luzon Ronson sold more apartments than ever in Q3, but smaller and cheaper per square meter

Luzon Ronson signed 16 contracts at its Sde Dov project in Q3 at about NIS 64,000 per sqm. What is behind the drop, and where the soil contamination stands

23 November 2026

Record collapses in Israeli construction: about 815 building and infrastructure firms failed in 2026, and listed builders' profitability was cut by more than half

CofaceBDi survey: about 815 Israeli construction and infrastructure firms collapsed in 2026, 85% more than in 2022. 93% of contractors report higher costs.

23 November 2026

Israel's construction input index rose 3.9% in a year, but builders talk of 20%: what it means for off-plan buyers

Construction wages rose 5.3% a year, oil jumped 45% and contractors report costs 20% above pre-war levels. What it means for buyers, builders and tenders

23 November 2026