Bid NIS 683 million more but never reached the price stage: lessons from the Highway 6 North tender ruling

A Jerusalem court dismissed Via Nova's petition against Shapir's Highway 6 North win. A 15% cap on revenue forecasts decided the tender.

Published: · 5 min read

This story was written with AI assistance, based on the sources linked at the end, and fact-checked. Responsible editor: אריאל סיבקוב. Found an error? Tell us.

Translated from the Hebrew original with the assistance of AI. Read the Hebrew original

The Jerusalem District Court on Sunday, November 15, 2026, dismissed a petition by the Via Nova consortium against Shapir Engineering's win in the tender to extend Highway 6 (the Cross-Israel Highway) north, covering segments 8 and 9. According to Globes and Nadlan Center, the losing group offered the state a concession fee about NIS 683 million higher than the winner's, yet its price envelope was never opened. The deciding factor was a single tender rule: a cap on how optimistic a bidder may be in its traffic and revenue forecast. Via Nova said it intends to appeal to the Supreme Court.

What is being built, at what cost and when

According to Bizportal and ice, which reported the award on July 16, 2026, the project covers about 22 kilometers from the Sumakh area to Beit HaEmek: a dual carriageway with three lanes in each direction and three new interchanges – Avelim, Mekhar and Beit HaEmek. Construction investment is estimated at about NIS 2 billion, and Bizportal puts the value of the project over the full concession, including operation and maintenance, at about NIS 12 billion, linked to the consumer price index.

The tender follows a public-private partnership (PPP) model: the concessionaire finances, builds, operates and maintains the road for 34 years. Six groups submitted bids. The tender committee was chaired by the senior deputy accountant general and included representatives of the Finance Ministry, the Transport Ministry, Cross Israel Highway and Inbal. The concession agreement with Shapir was signed on September 16, 2026. Works are expected to begin during 2027, with the road planned to open to the public in 2030.

The deciding rule: a 15% cap on the forecast

In toll road tenders, a high offer to the state usually rests on the assumption that many drivers will use the road and pay. To avoid accepting a bid that looks good on paper but depends on an unrealistic forecast, the tender stated that if a bidder's revenue forecast is more than 15% above the state's, its financial model would be tested against the state's forecast plus 15% only.

According to Globes, Via Nova projected revenue of about NIS 20.9 billion over the concession, compared with about NIS 12 billion in the state's forecast – roughly 74% higher. Nadlan Center reported that for 2030 the state estimated about 45,500 vehicles a day on the Avelim–Hilazon section, against about 62,000 in the consortium's forecast. Once the forecast was adjusted to about NIS 13.8 billion, Via Nova's financial model scored 48.03 points, below the 60-point passing threshold. According to Globes, the average debt service coverage ratio fell from 1.15 to 1.04, close to the 1.01 minimum, and the expected return on equity turned negative.

Because the bid did not pass the quality stage, its price envelope was not opened. As Globes notes, the gap of about NIS 683 million – about NIS 1.34 billion in Shapir's bid versus about NIS 2.02 billion in Via Nova's – is therefore only an apparent comparison.

What the petitioner argued and what the judge ruled

According to Nadlan Center, Via Nova argued that the committee deducted about 40 points, while in its view the tender documents allowed a reduction of only four, and that it was penalized twice for the same forecast. Judge Ilan Sela rejected the arguments. He ruled that the committee acted in line with the tender terms, and that the cap is a uniform rule set in advance for all bidders, meant to reduce the risk borne by the state.

The court also addressed timing. The consortium knew in July that it had not passed the threshold but filed the petition only on October 14, almost a month after the concession agreement had been signed. The judge saw this as a significant delay. The petitioner was ordered to pay NIS 150,000 in costs: half to the state and half to Shapir and its partners. This was not the tender's first legal round: in February 2026 Shapir petitioned to disqualify Via Nova over a bank guarantee defect, and the Supreme Court rejected its appeal on May 18.

What it means for infrastructure tender bidders

  • A high price is not enough. In many PPP tenders a bid must first pass a financial robustness gate, and only then is the price examined. A model that holds up only under an optimistic forecast may be disqualified before anyone sees the number.
  • Build the model on the state's forecast too. When there is a cap, a bidder needs to make sure financing, debt coverage ratios and returns meet the threshold even after the adjustment.
  • Challenge deadlines matter. The ruling stresses that a bidder who waits to petition, especially after the agreement is signed, weakens its chances.
  • The state takes on part of the demand risk. According to Bizportal, the state will give the concessionaire a safety net against demand risk – another reason it insists on conservative forecasts.

And what it means for drivers in the north

The new segments will be a toll road. Under the government decision reported by Bizportal and ice, frequent users will get a 40% discount on the toll rate, but eligibility terms have not yet been published and are expected closer to the road's opening. The concessionaire and the concession agreement are already in place. It is not yet clear whether the appeal Via Nova announced will affect the timetable.

Report an error

Spotted a factual error, a wrong quote or a broken link? Tell us. Every report is reviewed.

You are not legally required to provide these details. Fields marked * are needed to handle your request; without them we cannot reply. Purpose: to check the error report and update you. Database controller: אריאל סיבקוב (27news), news@esh27.com. Details are not shared with others, except infrastructure providers that store them for us (Cloudflare). You may access and ask to correct your data (sections 13–14 of Israel’s Privacy Protection Law). More: privacy policy.

This story was written with AI assistance and fact-checked. Editor: Ariel. Publishing & oversight policy

More in Infrastructure & EnergyWhole desk →

13 new power plants by 2040, mostly in central Israel: what Decision 2282 says, and why Emek Hefer went to the High Court

Israel is advancing gas plants near demand centres, on sites chosen by developers. The High Court asked how the state will prevent clustering in the Sharon

23 November 2026

COP31 collapsed without a deal. Why what is already happening in Brussels matters more to Israeli exporters

The Antalya summit ended with no fossil-fuel deal, but the EU carbon border tax has applied since January 2026. What it means for Israeli industry

23 November 2026

Driverless metro: a NIS 30 billion tender will decide who programs Tel Aviv's trains

NTA's Infra 2 tender will pick the systems for a fully automated GoA4 metro. What it covers, how the world does it and what regulation leaves open

23 November 2026

Israel's Electricity Authority proposes extending the urban solar premium to 2030, but shortening payments: what it means if you are planning a solar roof

The hearing on extending Israel's urban solar premium (6 agorot/kWh) closes tomorrow. New systems would get it until 2037, not 2042; standalone storage is out.

22 November 2026