13 new power plants by 2040, mostly in central Israel: what Decision 2282 says, and why Emek Hefer went to the High Court
Israel is advancing gas plants near demand centres, on sites chosen by developers. The High Court asked how the state will prevent clustering in the Sharon
This story was written with AI assistance, based on the sources linked at the end, and fact-checked. Responsible editor: אריאל סיבקוב. Found an error? Tell us.
Translated from the Hebrew original with the assistance of AI. Read the Hebrew original
Israel is entering a new wave of natural-gas power plants, and this time most of them are planned in the centre of the country rather than the periphery. The basis is Government Decision 2282 of October 2024, which set how many power-plant plans each electricity demand zone needs. According to an analysis published by Calcalist on November 23, 2026, this means about 13 new plants by 2040, with a combined capacity of about 9,000 megawatts. Last week the High Court of Justice heard petitions by regional councils in the Sharon region against plants in their areas, and the hearing ended without a ruling.
What the decision says
The decision, dated October 31, 2024, divides the country into demand zones (1a, 1b, 2, 3, 4 and 5). Each zone is assigned a number of required gas-plant plans, each of at least 630 MW, for a total of 19 plans. A timing table in the decision's annex sets how many plants must operate in each period: in zones 1 to 3, five plants in 2031–2035 and four more in 2036–2040; in zones 4 and 5, two plants each by 2035. That adds up to 13 plants by 2040.
The gap between 19 and 13 is deliberate. The state describes the plans as a "planning inventory": more sites are planned than will actually be built, so that a delay at one site does not leave a zone short of power. According to Calcalist, the state stresses that not all planned plants will be built.
Why the centre
According to Calcalist, the decision rests on three principles. The first is electricity demand growth of at least 3% a year. According to the report, Noga, Israel's electricity system operator, has since raised its forecast to about 3.5% a year, though no official figure has been published. The second is building plants near demand centres, to save on expensive transmission lines and avoid adding pollution in the south. That is why most plants are planned in the Sharon, the Shfela (central lowlands) and the Jerusalem area. Noga and the Electricity Authority had earlier warned of a possible power shortage in the Tel Aviv area.
The third principle is that private developers propose the sites themselves. A developer leases land, usually from a kibbutz or moshav, and applies to the Energy Ministry. The Planning Administration checks feasibility. The decision rules out approved residential areas, nature reserves and national parks, the coastal environment and highly sensitive hydrological areas. It favours sites near industrial zones and existing infrastructure, and requires applicants to map existing and approved plants within a 10-kilometre radius. It does not set a numerical minimum distance from homes.
After the review, the minister brings a "certification" decision to the cabinet. The developer then prepares a national infrastructure plan and submits it to the National Infrastructure Committee. Certification is not a licence and not a commitment to approve. A recent example: in October 2026 the government certified Ashdod Refineries to plan a gas-fired power plant on the refinery site. According to Calcalist, after planning the developers compete in a tender on the lowest electricity price.
The money involved
One developer told Calcalist that initiating a project costs about NIS 70 million, and that profit potential is about NIS 200 million a year once the capital is repaid. Landowners benefit too. According to a Shomrim investigation from May 2026, a proposal presented to the two Gvat Haim kibbutzim in Emek Hefer spoke of income of NIS 10–13 million a year for each kibbutz.
What happened at the High Court
The Emek Hefer and Menashe regional councils petitioned against four gas plants in their areas. Emek Hefer council head Dr. Galit Shaul says she does not oppose power plants but the way they are being advanced. According to her, five plants are planned in Emek Hefer and its surroundings, in addition to the two plants in Hadera. The petition argues that there is no comprehensive planning and that an unusual concentration of plants is forming in an area already exposed to air pollution.
According to Calcalist, last week's hearing ended without a decision. The judges asked the state to explain in writing how a concentration of many plants in a small area will be prevented. The state's position is that initial certification and detailed planning are separate: environmental impact, distance from housing and other factors are examined at the National Infrastructure Committee, where the concentration argument will also be reviewed. The state also said that only two more plants will be built in zone 2, from Binyamina to Herzliya. The Energy Ministry said the decision was advanced through the Economic Arrangements Law before the inter-ministerial team finished its work, but that it reflects the principles the team agreed on.
What about pollution
The new plants are due to run H-class turbines with improved filtering, so they are expected to pollute less than gas plants built a decade ago. But when gas is short and they switch to diesel, pollution rises. For comparison, according to the 2025 polluters index cited by Calcalist, local pollution damage from the coal-fired Orot Rabin plant in Hadera is estimated at NIS 532 million a year. For the Hagit East gas plant the estimate is NIS 19 million.
What it means for you
For residents of the Sharon, the Shfela and the Jerusalem area: such plans sometimes become public only after planning has started. It is worth tracking plans deposited at the National Infrastructure Committee, because that is when objections can be filed. For electricity consumers: plants close to demand save transmission costs, and a tender on the lowest price should eventually reach the bill. For kibbutzim and moshavim: lease income is high, but it stirs disputes within the community and with neighbours.
Next steps: the state's written answer to the High Court, and Noga's demand forecast to 2050. According to Calcalist, Noga is expected to present a forecast in which electricity demand doubles.
Sources
- כלכליסט – עמק הארובות: למה חזרו להקים תחנות כוח מזהמות, ודווקא בשרון? (23.11.2026)
- מזכירות הממשלה – החלטה 2282: קידום הביטחון האנרגטי של משק החשמל הישראלי (31.10.2024)
- שומרים – בקיבוצים רוצים לגדל תחנות כוח (18.5.2026)
- ביזפורטל – הממשלה נותנת לבז״א אור ירוק לתכנון תחנת כוח חדשה באשדוד (6.10.2026)
- TheMarker – בג״ץ לא ממהר לבלום תחנות כוח בעמק חפר (19.11.2026)
In this story
Report an error
This story was written with AI assistance and fact-checked. Editor: Ariel. Publishing & oversight policy