Shikun & Binui heads for PennDOT's largest-ever contract: a $1.29 billion bridge in Harrisburg
A Shikun & Binui joint venture bid about 19% below its rival to replace the I-83 bridge in Harrisburg. What is known, what is still open, and what it means
This story was written with AI assistance, based on the sources linked at the end, and fact-checked. Responsible editor: אריאל סיבקוב. Found an error? Tell us.
Translated from the Hebrew original with the assistance of AI. Read the Hebrew original
A joint venture in which Israel's Shikun & Binui holds 80% submitted the lowest bid to replace the John Harris Memorial (South) Bridge, which carries Interstate 83 over the Susquehanna River between Lemoyne and Harrisburg, Pennsylvania's capital. The Pennsylvania Department of Transportation (PennDOT) announced on November 13, 2026 that the venture is the "apparent low bidder" on the roughly $1.3 billion project, which it calls the largest construction contract in the department's history. The company reported the bid to the Tel Aviv Stock Exchange on November 16. The contract has not yet been signed.
What was bid
According to PennDOT, the low bid of about $1.289 billion came from a joint venture of Joseph B. Fay Company and New Enterprise Stone & Lime. Fay is a US construction company in the Shikun & Binui group (S&B USA). The second bid, from a venture led by Wagman Heavy Civil with J.D. Eckman and Brayman Construction, was about $1.586 billion.
The gap is roughly $297 million: the winning-track bid is about 19% below its competitor. Shikun & Binui's 80% share is worth about $1.03 billion, or about NIS 3.26 billion according to the company's filing as reported by Globes and ice. The whole project is valued at about NIS 4.1 billion.
What the project includes
- Replacing the South Bridge over the Susquehanna, one of the main crossings into the state capital.
- Reconfiguring the Lemoyne interchange and replacing the South Third Street bridge.
- Rebuilding the viaduct from the river to Route 230 (Cameron Street), including the Front Street interchange.
PennDOT says construction will start in 2027 and run through 2039, in phases that keep traffic moving. The state secured a $500 million federal grant in 2024 under the US infrastructure law, which will cover a large part of the cost. PennDOT calls it the largest federal transportation grant Pennsylvania has ever received.
Why it is not yet a "win"
Some Israeli headlines called it a win, but formally it is still the apparent low bid. PennDOT will review the bidder's documents. If they are complete, the contract will be awarded and a notice to proceed issued within six to eight weeks of the bid opening. If all goes to plan, signing is expected in late 2026 or early 2027.
What it means for Shikun & Binui
Backlog. According to Bizportal and ice, the company's US backlog stood at about NIS 3 billion at the end of June 2026. This project alone is larger than that entire backlog and would more than double it.
Contract type. The company says it is a construction-only contract: the owner did the design, so the company carries no design risk. In its filing it said the expected gross margin will not be below its usual pricing for such work. In an interview with Bizportal, CEO Amit Birman said the margin is in double digits.
Division of work. According to Birman, the US partner, which owns quarries and materials plants, handles the land work and supplies materials, while Shikun & Binui handles the in-river work. He said the materials prices the partner committed to made the low bid possible.
Timeline. The owner estimates about 11 years of work. Birman said the company can complete it in eight. That is the company's estimate, not a published contractual commitment.
Market. According to Bizportal, the shares rose about 5% intraday on the day of the report.
Open questions
A gap of about 19% is large, and investors will ask whether the price leaves enough margin on a project lasting more than a decade. The contract is in dollars, so its shekel value in the company's reports will move with the exchange rate. Birman also noted that such projects require a performance bond covering the full value of the work, which demands substantial financial strength from the partners.
Background: Shikun & Binui in Pennsylvania
The company is not new to the state. According to the S&B USA website, its US arm holds 40% of PennDOT's Major Bridge P3 Program, a public-private partnership that reached financial close at $2.3 billion. The program covers 23 structures at six interstate locations and is expected to be completed in 2028.
For Israeli readers, the story reflects a broader trend: Israeli infrastructure companies are seeking growth in the US, where federal infrastructure-law money is funding large bridge and highway projects.
What to watch
- Contract signing and the notice to proceed in the coming weeks, and the company's immediate filing on it.
- The project's effect on the backlog in the company's next reports.
- The start of work in 2027 and progress against PennDOT's schedule.
Sources
- PennDOT – Apparent Low Bidder for $1.3 Billion I-83 John Harris Memorial (South) Bridge Replacement Project (13.11.2026)
- גלובס – שיכון ובינוי זכתה במכרז ענק של 1.3 מיליארד דולר בארה"ב (16.11.2026)
- ביזפורטל – שיכון ובינוי הציעה 19% פחות מהמתחרים (16.11.2026)
- ביזפורטל – ראיון עם מנכ"ל שיכון ובינוי עמית בירמן (16.11.2026)
- אייס – שיכון ובינוי צפויה להקים גשר בהיקף של 4.1 מיליארד שקל (16.11.2026)
- Ynet Global – Israeli construction giant wins $1.3 billion Pennsylvania bridge contract (17.11.2026)
- S&B USA – PennDOT Major Bridge P3 Program
In this story
Report an error
This story was written with AI assistance and fact-checked. Editor: Ariel. Publishing & oversight policy