Israel's gas power plant wave: three decisions in two weeks and more than 3,600 MW in the pipeline
Three gas plants and two solar sites certified, Sorek financed, Sonol plans a plant beside a data center. What it means for bills and neighbours
This story was written with AI assistance, based on the sources linked at the end, and fact-checked. Responsible editor: אריאל סיבקוב. Found an error? Tell us.
Translated from the Hebrew original with the assistance of AI. Read the Hebrew original
Within a single week in early November 2026, three moves signalled where Israel's electricity sector is heading over the next decade. On November 4, a NIS 4.8 billion financing agreement was signed for the Sorek power station. On November 10, Sonol, Afcon and Pentalight signed a memorandum of understanding for a plant of about 900 megawatts next to a data center. And on November 11, the government opened a fast-track planning route for three new natural gas power plants and two large solar facilities. Together that is more than 3,600 megawatts of new generating capacity, at very different stages of planning and financing.
What the government approved on November 11
The decision is called a "certification". It allows developers to prepare a national infrastructure plan and submit it to the National Infrastructure Committee, which handles projects of national importance on a shortened track. Certification is not a generation licence under the Electricity Sector Law and is not a commitment to approve the plan. The decision itself lists open issues that could delay or change some of the plants.
The three gas plants:
- Menashe (Gan Shmuel) – Shamir Energy, next to the regional council's wastewater plant. Because of a possible conflict with a planned light-aircraft airfield, an aerial survey and Civil Aviation Authority approval are required. This is at least Shamir's second certification this year, after a plant in Emek Hefer approved in January.
- Jatt – PowerGen, next to the wastewater treatment plant between Route 6 and Route 581. The committee will weigh it against the expansion plans of nearby communities.
- Palmachim – Park Palmachim, in the industrial zone east of the kibbutz, leaving room for the expansion of the neighbouring desalination plant.
Each plant will have at least 630 megawatts, about 1,900 megawatts combined. According to reports, the developers are expected to request about 900 megawatts each, which could bring the total close to 2,700 megawatts. Grid connection is expected in the early 2030s at the earliest.
The two solar facilities are agrivoltaic projects on farmland: PowerGen's in the western Galilee and Nofar Energy's in the western Negev. Each will cover more than 1,000 dunams (about 250 acres), deliver 100 to 150 megawatts to the grid and include storage. The Energy Ministry presents them as part of strengthening energy security in the north and south and meeting the 2030 renewable energy target.
Sorek: the plant that already has the money
The Sorek station, with about 850 megawatts, will be built next to the Sorek desalination plants and the Shafdan wastewater plant. Its cost is estimated at about NIS 5.6 billion, and the NIS 4.8 billion financing is led by Mizrahi Tefahot Bank and Discount Bank. The project follows a BOT model: the concessionaire will operate the plant for almost 25 years and then hand it over to the state.
According to Israel Hayom, the tender, run by the Accountant General at the Finance Ministry, was won in December 2024 by Adletech and Menora Mivtachim, at an availability tariff of 3.18 agorot per available kilowatt-hour. One important detail: at first the plant will be entitled to availability payments for only 670 megawatts, because of transmission grid constraints. In other words, the bottleneck is not only generation but also the lines that carry the power.
Sonol, Afcon and Pentalight: a power plant and a data center on one site
The memorandum signed on November 10 covers a gas plant of about 900 megawatts, a data center of up to 200 megawatts and a storage facility. The investment in the power plant alone is estimated at about NIS 4 billion. The planned joint company would be held 45% by Sonol, 27.5% by Afcon and 27.5% by Pentalight. It is a commercial memorandum, not a government approval, but it fits the model favoured by the Electricity Authority and Noga: data centers located next to the generation source instead of loading the national grid.
Why now
Noga, the electricity system operator, has previously estimated that at least 9,000 additional megawatts will be needed by 2040. The drivers: AI data centers, the shift to electric vehicles and population growth. According to Calcalist reports, data center connection requests submitted to Noga total about 27,000 megawatts, and the Electricity Authority has capped each new data center at 200 megawatts. In Israel, building a power plant takes more than a decade from initiation to operation, so today's decisions determine the electricity supply of the 2030s.
The objections
The road is still long. The Palmachim plant was removed from the government agenda in early October after the Gan Raveh regional council demanded consultation and an impact review, and the council is considering legal steps. The Ministry of Environmental Protection also voiced reservations, arguing that expanding storage could reduce the need for more gas plants. The Yavne municipality is pursuing legal action against a plant in northern Ashdod that was certified in October, and Sharon-area mayors are worried about environmental and health effects and limits on town expansion. According to reports, the Attorney General's office cautioned against advancing plans during a transitional government, and the decisions were approved because they implement earlier policy and only allow plans to be submitted.
What it means for you
- For households: no immediate effect on the bill. Most of the plants will not operate before the early 2030s. In the long run, availability payments like Sorek's are a cost usually built into the tariff, so the winning prices in tenders matter to everyone.
- For residents near the sites: a national infrastructure plan is deposited for public objections. That is the stage where location, distances and environmental conditions can be influenced.
- For businesses and data center developers: the trend is clear – generation, storage and consumption on the same site. Anyone planning a data center without an adjacent power source should expect a longer wait for a grid connection.
Sources
- Bizportal – עד 2,700 מגה-וואט בגז: שמיר, פאוורג'ן ופלמחים מקבלות הסמכה לתחנות כוח (11.11.2026)
- ישראל היום – עסקת ענק במשק האנרגיה: 4.8 מיליארד שקל להקמת תחנת כוח חדשה (4.11.2026)
- מעריב – סונול, אפקון ופנטלייט מקדמות הקמת תחנת כוח וחוות שרתים (10.11.2026)
- Audiatur-Online – Israel plant drei neue Gaskraftwerke und zwei Solarfelder (12.11.2026)
In this story
Report an error
This story was written with AI assistance and fact-checked. Editor: Ariel. Publishing & oversight policy