Israel's solar connections slump: 2026 heads for the weakest year since 2020 as the state leans on gas again

Only 612 MW of solar was connected to Israel's grid in nine months, and over half of requests were rejected. What is holding solar back, and what it means for you

Published: · 4 min read

This story was written with AI assistance, based on the sources linked at the end, and fact-checked. Responsible editor: אריאל סיבקוב. Found an error? Tell us.

Translated from the Hebrew original with the assistance of AI. Read the Hebrew original

Israel's solar market, which posted a record year for grid connections in 2025, has braked sharply. According to Electricity Authority data published by Calcalist on November 11, 2026, only 612 MW of solar capacity was connected to the grid in the first nine months of the year, and the total is expected to stay below 850 MW by year-end. That would make 2026 the weakest year for connections since 2020. The trade journal MEES, reviewing Israel's power sector on November 20, likewise says renewable connections are on course for their weakest year since 2020.

The slowdown comes just as electricity demand accelerates, partly because of data centers and artificial intelligence, and on the same day the government advanced three new gas-fired power plants.

Requests soared, approvals did not

The gap is not about lack of interest. According to the same data, connection requests totaling 7,246 MW were filed in the first nine months of 2026 – more than in all of 2025. But 54% of the requested capacity received a negative answer, apparently because of grid capacity limits.

The Electricity Authority says the decline stems mainly from extensions granted to developers on mandatory connection deadlines, mostly in high-voltage projects, including agrivoltaic facilities that were at advanced planning stages. The Energy Ministry points to grid saturation: according to Calcalist, Ron Eiffer, head of the ministry's sustainable energy division, said the problem is neither economics nor land, but the grid. Eitan Parnass, CEO of the Green Energy Association of Israel, adds regulatory fragmentation: a project needs approvals from Noga (the system operator), the Israel Electric Corporation, the Planning Administration, the Environmental Protection Ministry and, on farmland, the Agriculture Ministry. A government source quoted in the report said some projects were delayed by up to 20 months.

Rooftops, meanwhile, are at a record

The exception is private rooftops. Small installations, mostly on roofs, added 134 MW in nine months, and more than 180 MW is expected by year-end. The Energy Ministry expects 2026 to be a record year in the residential segment.

Part of the explanation is a race against the clock. On October 19 the Electricity Authority published a new framework through 2030 for public comment. According to Globes, the fixed tariff for new rooftop systems, currently 48 agorot per kWh (54 agorot in cities with an urban premium), will fall gradually – by about 5% a year – to roughly 35 agorot in 2030. Under the proposal, existing systems, and those that file a connection request by the end of 2026 and complete installation within a year, keep the current tariff for 25 years. Systems installed from 2027 will receive a tariff only until the end of 2047. According to Bizportal, comments were accepted until November 10, and a final decision is expected in the coming months.

Gas moves back to center stage

On November 11 the government approved fast-track planning at the National Infrastructure Committee for three gas-fired plants – in Jatt (900 MW, PowerGen), in the Menashe Regional Council (Kesem, the energy arm of Mivtach Shamir) and at the Palmachim industrial park – as well as two large solar projects in peripheral regions. According to MEES, the three plants would add at least 1.89 GW and possibly up to 2.7 GW. Noga estimates another 4.7 GW of gas-fired capacity will be needed by 2035, about 36% of the 13.2 GW installed at the end of 2025.

The government target – 30% of electricity from renewables by 2030 – looks distant. According to Calcalist, renewables stood at about 16% last year, and the industry estimates Israel is roughly two years behind and will reach the target only in 2032. The next target, 35% by 2035, has not yet been approved by the energy minister. The Environmental Protection Ministry, in a letter described by CTech on November 17, estimated that offsetting the extra pollution from data centers would require a target of about 45% by 2035.

What it means for you

  • Homeowners with roofs: Under the proposal, filing a connection request by the end of 2026 and completing installation within a year locks in the current tariff for 25 years. After that, the tariff falls and the term gets shorter. Check with your installer when the request is actually filed, and follow the final wording of the decision.
  • Farmers and landowners: Large facilities depend on grid capacity, and more than half of the capacity requested this year was rejected. Under the proposal, from January 2028 connection priority will go to projects offering a lower cost to the economy.
  • Electricity consumers: According to the Electricity Authority, renewable support accounts for about 10% of the household tariff. On the other hand, fewer solar connections combined with more gas plants may increase the power sector's exposure to gas prices.
  • Developers and investors: The bottleneck is the grid, not demand. The pace of investment in transmission and storage will determine how fast connections recover in the coming years.
Report an error

Spotted a factual error, a wrong quote or a broken link? Tell us. Every report is reviewed.

You are not legally required to provide these details. Fields marked * are needed to handle your request; without them we cannot reply. Purpose: to check the error report and update you. Database controller: אריאל סיבקוב (27news), news@esh27.com. Details are not shared with others, except infrastructure providers that store them for us (Cloudflare). You may access and ask to correct your data (sections 13–14 of Israel’s Privacy Protection Law). More: privacy policy.

This story was written with AI assistance and fact-checked. Editor: Ariel. Publishing & oversight policy

More in Infrastructure & EnergyWhole desk →

13 new power plants by 2040, mostly in central Israel: what Decision 2282 says, and why Emek Hefer went to the High Court

Israel is advancing gas plants near demand centres, on sites chosen by developers. The High Court asked how the state will prevent clustering in the Sharon

23 November 2026

COP31 collapsed without a deal. Why what is already happening in Brussels matters more to Israeli exporters

The Antalya summit ended with no fossil-fuel deal, but the EU carbon border tax has applied since January 2026. What it means for Israeli industry

23 November 2026

Driverless metro: a NIS 30 billion tender will decide who programs Tel Aviv's trains

NTA's Infra 2 tender will pick the systems for a fully automated GoA4 metro. What it covers, how the world does it and what regulation leaves open

23 November 2026

Israel's Electricity Authority proposes extending the urban solar premium to 2030, but shortening payments: what it means if you are planning a solar roof

The hearing on extending Israel's urban solar premium (6 agorot/kWh) closes tomorrow. New systems would get it until 2037, not 2042; standalone storage is out.

22 November 2026