Dalia Energy lifts profit 22%, but an Eshkol unit is down until January: covenant risk and the Leviathan gas dispute

Q3 net profit of NIS 132m, driven mainly by lower finance costs; a fault at Eshkol unit 34 may lead to covenant breaches in some quarters of 2027

Published: · 4 min read

This story was written with AI assistance, based on the sources linked at the end, and fact-checked. Responsible editor: אריאל סיבקוב. Found an error? Tell us.

Translated from the Hebrew original with the assistance of AI. Read the Hebrew original

Dalia Energy Companies, one of Israel's largest private power producers and controlled by Mashk Energy, ended the third quarter of 2026 with net profit of about NIS 131.7 million, up 22% from the same quarter last year. But the results, published on November 19, also reveal a fault at a generating unit of the Eshkol power station in Ashdod that could cause the subsidiary to miss its loan covenants in some quarters of 2027, and an open dispute with the Leviathan partners over a gas deal meant to supply two new power plants.

The numbers: profit up, operations nearly flat

According to the results as reported by Ice, Bizportal and Globes, third-quarter revenue reached about NIS 968.5 million, compared with about NIS 853.5 million in the same quarter of 2025, growth of about 13.5%. Operating profit, however, was almost unchanged at about NIS 229 million.

What lifted the bottom line was mainly financing: net finance expenses fell to about NIS 46 million from about NIS 71 million a year earlier, a drop of about 35%. Bizportal stressed that most of the improvement in net profit came from financing rather than operations. According to Globes, revenue growth is linked to expanding electricity supply to private customers, following Electricity Authority tenders that let private suppliers buy power more cheaply.

In the first nine months of the year revenue totaled about NIS 2.28 billion (up about 10%), and net profit reached about NIS 147.5 million, compared with about NIS 91.4 million in the same period, a jump of about 61%.

Eshkol unit 34: damage found during maintenance

The Eshkol station was bought from the Israel Electric Corporation in June 2024, as part of the electricity sector reform, for about NIS 9 billion. Unit 34 was taken offline on October 3 for planned maintenance, and unexpected damage was found during the work. According to Globes, the unit has a capacity of 360 megawatts and the fault was in a seal in the generator. The return to full commercial operation has been pushed to January 2027, about a month later than planned.

The company estimates that the longer maintenance and extra costs could materially affect the results of Eshkol Production, depending on the insurance proceeds received. Eshkol Production has notified its insurers that it intends to file a claim. According to an estimate cited by Globes, repair costs and lost revenue amount to tens of millions of shekels. The company said this is not a material event, so it was not reported earlier. Globes also noted there is no risk of a power shortage, because only one unit is affected and it is winter, when demand is lower than in summer.

The covenant risk

The more sensitive part concerns debt. According to Bizportal, Eshkol Production's senior debt stood at about NIS 4.45 billion at the end of September, with final maturity in December 2043. As of the end of September the company met all its financial covenants, but it says it may not meet them in some quarters of 2027. The company and its shareholders are preparing for the possibility that they will have to inject funds to prevent a breach of the financing terms. According to Globes, the lenders include Bank Hapoalim and Mizrahi Tefahot.

The Leviathan gas dispute

In May 2026 an agreement was signed to supply Leviathan gas to two new power plants Dalia is developing, at Eshkol and at the Tzafit site. In September NewMed Energy and Ratio announced they were cancelling the agreement, arguing that the conditions precedent were not met on time. Dalia disputes this, saying that Competition Authority approval, received on October 6, completed the conditions and the agreement entered into force. On October 22 Dalia opened international arbitration in London, asking for a ruling that the cancellation notice is invalid. The proceeding is still pending.

The dispute is already affecting financing: on November 12 Midroog rated the senior debt of the Dalia Expansion project A2.il but placed it under review with negative implications, citing uncertainty over the gas agreement. According to Bizportal, the Tzafit plant, at about 850 megawatts, is expected to start operating in the fourth quarter of 2028 at an estimated cost of about NIS 3.9 billion, and the new Eshkol plant, also about 850 megawatts, is expected to operate in 2029.

Data center: another test on the grid

Dalia is also advancing a data center on land it owns in Ashdod. According to Ice, a new memorandum of understanding was signed in August with Serverfarm and the Israel Infrastructure Fund, with exclusive negotiations until November 30, 2026. Under the Electricity Authority's proposed regulation, if adopted as drafted, the company may have to post a guarantee of up to NIS 400 million for a grid connection.

What it means

Dalia's shares are not traded on the stock exchange, but its bonds are. For bondholders, the next test is unit 34's return in January and the size of the insurance payout. For the power sector, the bigger question is gas: without secure supply, two plants with a combined capacity of about 1,700 megawatts face open questions over financing and timelines. And for investors in Mashk Energy, which holds about 50.2% of Dalia, the results show that the profit improvement currently rests more on financing than on operations.

Report an error

Spotted a factual error, a wrong quote or a broken link? Tell us. Every report is reviewed.

You are not legally required to provide these details. Fields marked * are needed to handle your request; without them we cannot reply. Purpose: to check the error report and update you. Database controller: אריאל סיבקוב (27news), news@esh27.com. Details are not shared with others, except infrastructure providers that store them for us (Cloudflare). You may access and ask to correct your data (sections 13–14 of Israel’s Privacy Protection Law). More: privacy policy.

This story was written with AI assistance and fact-checked. Editor: Ariel. Publishing & oversight policy

More in Infrastructure & EnergyWhole desk →

13 new power plants by 2040, mostly in central Israel: what Decision 2282 says, and why Emek Hefer went to the High Court

Israel is advancing gas plants near demand centres, on sites chosen by developers. The High Court asked how the state will prevent clustering in the Sharon

23 November 2026

COP31 collapsed without a deal. Why what is already happening in Brussels matters more to Israeli exporters

The Antalya summit ended with no fossil-fuel deal, but the EU carbon border tax has applied since January 2026. What it means for Israeli industry

23 November 2026

Driverless metro: a NIS 30 billion tender will decide who programs Tel Aviv's trains

NTA's Infra 2 tender will pick the systems for a fully automated GoA4 metro. What it covers, how the world does it and what regulation leaves open

23 November 2026

Israel's Electricity Authority proposes extending the urban solar premium to 2030, but shortening payments: what it means if you are planning a solar roof

The hearing on extending Israel's urban solar premium (6 agorot/kWh) closes tomorrow. New systems would get it until 2037, not 2042; standalone storage is out.

22 November 2026