ESH27 News – technology, the physical world, society and government
Infrastructure & Energy · Wing B – The Physical World

Tel Aviv's Purple Line completes licensing: what still stands between riders and a June 2028 opening

Israel’s National Licensing Authority has finished licensing the Purple Line. Service is planned for June 2028, after construction and test runs end.

Published: · 4 min read

This story was written with AI assistance, based on the sources linked at the end, and fact-checked. Responsible editor: אריאל סיבקוב. Found an error? Tell us.

Translated from the Hebrew original with the assistance of AI. Read the Hebrew original

The National Licensing Authority at Israel's Planning Administration announced on Tuesday (17 November 2026) that it has completed the licensing process for the Purple Line of the Tel Aviv metropolitan light rail. According to reports in Davar, Maariv and Nadlan Center, the process involved approving more than 100 work packages over roughly three years. Commercial service is now planned for June 2028 (Maariv reported June–July 2028). Licensing is not the finish line, however: NTA and the concessionaire still have to complete construction and run test trips before the first passengers board.

What exactly was completed

Licensing a transport project of this size is not a single permit but a long series of approvals for different parts of the line: track sections, stations, operational buildings and related infrastructure works. Completing the process means that, from the planning authorities' standpoint, every component of the line has received the required approvals. As Nadlan Center noted, it does not mean the work on the ground is finished.

Ron Rekah, head of the National Licensing Authority, called the milestone "real good news for residents of the metropolitan area and for Israel's mass transit system." He said the authority tried to balance fast progress with planning quality.

In practical terms, from now on delays on the line can no longer be blamed on the planning and approval stage. What remains is engineering work, including completing construction, installing systems, testing and commissioning, all of which is the responsibility of NTA and the concessionaire. This is also where the timetable is worth watching in the coming months: the next reports on the start of test runs will be a clear sign of whether the June 2028 target is still achievable.

The line in numbers

The Purple Line links Yehud-Monosson, Or Yehuda, Kiryat Ono and Ramat Gan with central Tel Aviv (according to Davar and Nadlan Center; Maariv also mentions Givatayim). It is about 27 kilometres long, a figure that appears both in a 2022 report on the tender award and in an Israel Hayom article from October 2026. The number of stations varies between sources, from 45 to about 50, probably reflecting design changes over the years.

The line is being built and maintained by a consortium of Shapir Engineering and Spanish rolling-stock maker CAF. According to a Funder report from January 2022, when Shapir announced the win, the company estimated the project's value over construction and maintenance at about NIS 9.2 billion, with a construction grant of about NIS 2.2 billion. The tender set a four-year construction period and a 21-year maintenance period.

The Ministry of Transport expects the line to carry tens of millions of passengers a year. In February 2025, Walla reported a forecast of about 256,000 passengers a day and a train every four minutes at peak times. These are planning figures, not measured ridership.

The road to 2028: a one-year delay

According to Davar, construction began in 2018. The original target was 2027, but in February 2025 NTA and the Ministry of Transport announced a delay of about a year. Reasons cited at the time included labour shortages, the departure of foreign consultants and import problems. Works on Allenby, Ben Yehuda and Arlozorov streets in Tel Aviv were described as a major cause of the delay.

The date now being reported, June 2028, roughly matches what was set in February 2025 (July 2028 according to Walla, "mid-2028" according to Tel Aviv Online). In other words, at least based on public information, there has been no further postponement since then.

What it means for residents, property owners and the housing market

For commuters: more than a year and a half remains until opening, and as long as construction continues, special traffic arrangements along the route may stay in place. Before service starts, NTA and the concessionaire will begin test runs and system checks. According to Maariv, approval to operate depends on the test runs passing without unusual faults.

For property owners: according to Nadlan Center, compensation for expropriations and loss of value on the Purple and Green lines combined is estimated at about NIS 1.7 billion. Most expropriations have been completed, but some claims are still open. Owners along the route who are considering a claim should check the deadlines that apply to them with a lawyer.

For the housing market: light rail lines are generally seen as a factor in demand for neighbourhoods along their route, especially in cities such as Yehud-Monosson, Or Yehuda and Kiryat Ono that have no rail today. Greater certainty about the opening date may strengthen that consideration for buyers and developers, but the date is not yet final.

The bigger picture

The Red Line has been running since August 2023. The Green Line is under construction: under the schedule published in February 2025, its southern section is expected to open at the end of 2028 and its northern section no earlier than 2030. If the Purple Line keeps to schedule, 2028 could be the year Gush Dan's light rail network grows from one line to three, at least partially.

For anyone following infrastructure tenders, the Purple Line is also a test of a model in which a private concessionaire is responsible for financing, design, construction and maintenance over many years. Licensing removes one planning hurdle; meeting the 2028 target now depends on execution on the ground.

Report an error

Spotted a factual error, a wrong quote or a broken link? Tell us. Every report is reviewed.

You are not legally required to provide these details. Fields marked * are needed to handle your request; without them we cannot reply. Purpose: to check the error report and update you. Database controller: אריאל סיבקוב (27news), news@esh27.com. Details are not shared with others, except infrastructure providers that store them for us (Cloudflare). You may access and ask to correct your data (sections 13–14 of Israel’s Privacy Protection Law). More: privacy policy.

This story was written with AI assistance and fact-checked. Editor: Ariel. Publishing & oversight policy

More in Infrastructure & EnergyWhole desk →

13 new power plants by 2040, mostly in central Israel: what Decision 2282 says, and why Emek Hefer went to the High Court

Israel is advancing gas plants near demand centres, on sites chosen by developers. The High Court asked how the state will prevent clustering in the Sharon

23 November 2026

COP31 collapsed without a deal. Why what is already happening in Brussels matters more to Israeli exporters

The Antalya summit ended with no fossil-fuel deal, but the EU carbon border tax has applied since January 2026. What it means for Israeli industry

23 November 2026

Driverless metro: a NIS 30 billion tender will decide who programs Tel Aviv's trains

NTA's Infra 2 tender will pick the systems for a fully automated GoA4 metro. What it covers, how the world does it and what regulation leaves open

23 November 2026

Israel's Electricity Authority proposes extending the urban solar premium to 2030, but shortening payments: what it means if you are planning a solar roof

The hearing on extending Israel's urban solar premium (6 agorot/kWh) closes tomorrow. New systems would get it until 2037, not 2042; standalone storage is out.

22 November 2026