Paid every month, not only at the end of the trial: Israeli developer ordered to pay buyers NIS 30,000 a month until handover

An Israeli court ordered a developer to pay buyers NIS 30,000 every month until their delayed apartment is delivered, before ruling on the claim itself.

Published: · 5 min read

This story was written with AI assistance, based on the sources linked at the end, and fact-checked. Responsible editor: אריאל סיבקוב. Found an error? Tell us.

Translated from the Hebrew original with the assistance of AI. Read the Hebrew original

Buyers of new apartments in Israel whose handover is delayed usually wait years for compensation: they file a claim, wait for a ruling, and meanwhile pay both rent and a mortgage. A decision by the Kfar Saba Magistrate's Court, reported by Calcalist on November 22, 2026, points to a different route. Judge Hagit Bolmash ordered a development company and its controlling shareholder to pay the buyers NIS 30,000 at the end of every month until the building receives its occupancy certificate (Form 4) and the unit is lawfully delivered. All of this comes before the main claim has been decided.

The case

According to the report, the buyers signed a contract on June 18, 2024 to buy a duplex in a TAMA 38/2 project in Tel Aviv for NIS 9 million including VAT. The contractual delivery date was February 18, 2025. At the time of the decision the delay had reached about 20 months, and the building still had no Form 4.

The buyers said they had already paid about NIS 8.1 million, roughly 90% of the price, into the project's escrow financing account, and that their financing costs run to about NIS 25,000 a month. They refused to live in the unit without a lawful occupancy permit.

The developer argued that Form 4 was expected within weeks, and that complaints and an administrative petition filed by the buyers were what delayed it. It also disputed the buyers' estimate of fair rent. These arguments will still be heard in the main claim.

What the court decided

The decision was given on a request for interim monetary relief, meaning a payment made while proceedings continue. The monthly payment applies retroactively from the date the request was filed, October 20, 2026, and will be credited against any compensation awarded at the end.

To balance this, the court made the payment conditional on the buyers depositing an undertaking to repay the money with linkage and interest if their claim fails or a lower amount is awarded. The developer may ask to reduce the sum if it presents an appraisal or rental contracts showing a lower rental value. It was also ordered to pay NIS 10,000 in costs.

According to the report, the judge found that the current situation is not stable, because the buyers' costs build up every month, and that rejecting the request would undermine the legislature's intent to give buyers monthly relief without waiting for the end of proceedings. She described the buyers as people who "see their apartment from afar".

The report does not explain how the NIS 30,000 figure was calculated. The only basis mentioned is an opinion by the buyers' appraiser on fair rent, which the developer disputes.

The legal basis: section 5A of the Sale Law

Section 5A of the Sale (Apartments) Law was changed by Amendment No. 9, published in June 2022 and applying to contracts signed from July 7, 2022. The contract in this case was signed in 2024, so it falls under the new regime. According to legal reviews of the law, these are its main points:

  • No need to prove damage. Compensation is based on the rent of a similar apartment in size and location, not on the buyer's actual expenses.
  • No compensation for the first month. Compensation starts only after a full month has passed since the contractual delivery date.
  • Rising tiers. At first compensation equals fair rent, then it rises to 125% of it, and from the 11th month of delay it reaches 150%.
  • Paid at the end of each month. According to a review by Merkaz HaNadlan, the law says compensation is paid at the end of each month for that month. This is the point the Kfar Saba decision relied on.
  • Narrow exemption. The developer is exempt if the delay was caused solely by the buyer, or by frustration circumstances under section 18(a) of the Contracts (Remedies) Law, when its conditions are met.
  • A better contract prevails. If the contract sets higher compensation, the contractual amount applies.

Contracts signed before July 7, 2022 fall under the previous regime: compensation only after a delay of more than 60 days, but then from day one, at 150% of rent for the first eight months and 125% after that.

What it means for buyers

The law set a monthly payment, but many buyers receive compensation only at the end of a lawsuit or in a settlement. A magistrate's court decision is not a binding precedent, and it was given at an interim stage. Still, it shows that buyers can ask the court to enforce the monthly payment while proceedings continue. Buyers facing a delay can:

  1. Check the contract date. It decides whether the new or the old regime applies.
  2. Document the contractual delivery date and every notice of delay from the developer.
  3. Get an estimate of fair rent for a similar apartment in the area, for example from an appraiser. It is the basis of the calculation, and in this case it is also the point of dispute.
  4. Weigh the risk. Interim relief may require an undertaking to repay the money with linkage and interest if the claim fails.
  5. Consult a lawyer before signing a waiver or a settlement.

What next

The main claim, for compensation over the roughly 20 months of delay that have already passed, is still pending, and the developer's arguments will be examined there. Until then, and until Form 4 is issued, the monthly payment is meant to continue.

Report an error

Spotted a factual error, a wrong quote or a broken link? Tell us. Every report is reviewed.

You are not legally required to provide these details. Fields marked * are needed to handle your request; without them we cannot reply. Purpose: to check the error report and update you. Database controller: אריאל סיבקוב (27news), news@esh27.com. Details are not shared with others, except infrastructure providers that store them for us (Cloudflare). You may access and ask to correct your data (sections 13–14 of Israel’s Privacy Protection Law). More: privacy policy.

This story was written with AI assistance and fact-checked. Editor: Ariel. Publishing & oversight policy

More in Law & RegulationWhole desk →

Traffic tickets by text within hours: what is changing in Israeli road enforcement, and how to avoid fake fine messages

Israel Police began texting traffic ticket notices within up to 12 hours, is adding about 200 cameras and uses drones. What drivers and owners should know

23 November 2026

Israel publishes draft Outer Space Law: permits for every launch, satellite operation and in-orbit sale

Israel proposes its first space law: licensing by the Israel Space Agency, a national registry of launched objects and mandatory insurance. What it means for industry

22 November 2026

Your ID card on your phone and government login at the bank: what Israel's national digital identity strategy proposes, with comments due Nov. 30

Israel's draft national digital identity strategy proposes a wallet for ID cards and driving licences and a gradual opening to private firms. Comments close Nov. 30.

22 November 2026

Inherited an apartment in an Israeli urban renewal project? Your elderly parent's tax benefits may not pass to you

Two Israel Tax Authority positions set out what heirs get in pinui-binui and TAMA 38. If a senior dies before the sale day, the tax benefits may be lost.

19 November 2026