Mega Or to build two more data centers for about $1.6 billion: 134 MW and NIS 550 million a year, but it all hinges on power approvals

Mega DC signed deals to build two data centers in Yoav and Beit Shemesh for a cloud and AI giant. They lapse if grid approvals are late.

Published: · 5 min read

This story was written with AI assistance, based on the sources linked at the end, and fact-checked. Responsible editor: אריאל סיבקוב. Found an error? Tell us.

Translated from the Hebrew original with the assistance of AI. Read the Hebrew original

Israeli income-producing real estate company Mega Or announced on November 18, 2026 that its wholly owned subsidiary, Mega DC, has signed two agreements to build and lease new data centers in Israel, with a combined capacity of about 134 MW IT. According to reports, construction is estimated to cost about $1.6 billion, and the company expects net operating income (NOI) of about NIS 550 million a year after delivery. But the agreements carry a material condition: if grid connection approvals do not arrive on time, the deal is cancelled.

What was signed

According to Bizportal and Sponser, the deal covers two facilities of about 67 MW IT each (67.2 MW according to Sponser). According to Sponser, one will be built in the Yoav Regional Council area, near Masmiya, and the other is Phase B of the company's site in Beit Shemesh. "MW IT" refers to the power allocated to the servers themselves, excluding cooling and auxiliary systems, so total draw from the grid is higher.

Construction is estimated at about $12 million per MW IT, or about $1.6 billion in total, roughly NIS 5.3 billion. Delivery is planned by the end of the second quarter of 2028. Each lease runs seven years from the delivery of that facility, with a client option to extend for five more years on the same terms. According to Sponser, delivery will be followed by about two months of client-specific fit-out work, for which the company expects additional payment.

The NOI of about NIS 550 million a year is the company's own estimate. For comparison, according to Bizportal, Mega Or's current annualized NOI across the whole company is about NIS 506 million, based on its third-quarter presentation. In other words, the two facilities alone are expected to generate more than all of the company's existing operations. By Bizportal's calculation, that is a yield of about 10% on construction cost.

Who is the client

Mega Or did not name the client. The announcement describes it as a subsidiary of an international cloud and AI company listed on Nasdaq, and according to reports it is the same client that signed earlier deals with Mega DC. Globes reported on November 19 that, according to information it obtained, the client is Nebius Group. In the sources reviewed, the companies have not officially confirmed this.

The earlier deals provide context. In May 2025 an agreement was signed for 8 MW at the company's data center in Modi'in. According to Globes, that facility opened in October 2025 with about 4,000 Nvidia GPUs, and a quarter of its capacity is earmarked for the Israel Innovation Authority's national supercomputer. In January 2026 another agreement was reported, for about 80 MW, about 22 MW at Masmiya and about 58 MW in Beit Shemesh, at a cost of about $880 million. Globes reported at the time that Nebius had confirmed the details. According to Bizportal, with the two new sites Mega DC is building eight facilities with a combined capacity of about 486 MW IT.

The condition that could cancel everything: electricity

The agreements are conditional on obtaining the required electricity approvals by set dates. According to Bizportal and Sponser, if the approvals are not received on time, the agreements will be cancelled with no compensation to either side, and the client will have a 12-month priority right to the capacity. The agreements also set compensation for delays and for failing to meet service levels, and the client may cancel under certain conditions.

This condition is not a formality. In July 2026 Israel's Electricity Authority issued an interim order freezing new grid connection permits for data centers for 140 days, after applications reached about 27,000 MW, Globes reported. On October 25 the authority published a hearing on a decision for connections above 8 MW: a quota of up to 1,000 MW plus up to 300 MW for local needs, a cap of 200 MW per data center, a guarantee of NIS 2 million per MW at the commitment stage, and, from January 1, 2028, possible load curtailment of up to 200 hours a year. Mega Or said at the time, in a filing cited by Investing.com, that it was still studying the hearing's provisions. According to published information, no final decision has yet been made.

What it means

For investors: Mega Or shares rose about 6.1% on November 18 to NIS 467, giving a market value of about NIS 17.8 billion, according to Bizportal. Financing for the new projects has not been disclosed. The main risk is the timetable for electricity approvals, which is outside the company's control.

For the market: the deal joins a wave of large data center projects in Israel, including the Enlight and Shemen Real Estate deal in Haifa announced this week. They are all competing for the same limited power quota, so the Electricity Authority's final decision will largely determine which projects actually get built, and when.

For businesses: more computing capacity inside Israel could help organizations that need to keep data in the country or cut latency, particularly companies developing AI models. But the new capacity is only planned for mid-2028, and only if the power arrives.

What to watch: the Electricity Authority's final decision following the hearing, and Mega Or's updates on the delivery of the facilities from the January deal, which according to reports at the time were to be handed over in stages between the third quarter of 2026 and the first quarter of 2027.

Report an error

Spotted a factual error, a wrong quote or a broken link? Tell us. Every report is reviewed.

You are not legally required to provide these details. Fields marked * are needed to handle your request; without them we cannot reply. Purpose: to check the error report and update you. Database controller: אריאל סיבקוב (27news), news@esh27.com. Details are not shared with others, except infrastructure providers that store them for us (Cloudflare). You may access and ask to correct your data (sections 13–14 of Israel’s Privacy Protection Law). More: privacy policy.

This story was written with AI assistance and fact-checked. Editor: Ariel. Publishing & oversight policy

More in Cloud & DataWhole desk →

Workday to buy Honeydew: the layer meant to stop AI agents improvising business math

Workday plans to acquire Honeydew, a 2022 startup also registered as an Israeli company in Ramat Gan. What it does and why it matters for enterprises

22 November 2026

Intel lands first external 18A customer as Microsoft adopts its packaging: what it means for Kiryat Gat

A first outside 18A customer, Microsoft adopts EMIB for Azure, and in Kiryat Gat a blast-hit fab and a frozen one. What it means for Israel

20 November 2026

Nvidia's networking business, born at Mellanox, topped $21 billion in a quarter: what it means for Israel's economy

Nvidia's networking revenue, from a business developed mainly in Israel, rose about 156% in a year to over $21B. What it means for growth and tech

18 November 2026

Matrix: shareholder profit jumps 48% as cloud leads growth – what it says about Israel's IT market

Q3 revenue rose to NIS 2.36 billion, about 14% in constant currency. Cloud is the fastest-growing unit as AI moves from pilots to deployment.

18 November 2026